PSEG - Construction Notice Update January 21, 2017

pseglogo

Updated: January 19, 2017

PSE&G ELECTRIC RELIABILITY IMPROVEMENTS

             UTILITY UNDERGROUND INFRASTRUCTURE UPGRADE

WORK SCHEDULE UPDATE: January 23, 2017 – January 27, 2017

               VILLAGE OF RIDGEWOOD

     Anticipated         Schedule

Activity

Location

Traffic Impact

Expected Parking Closures

January 23, 2017 January 27, 2017

Underground Manholes & Pipe Installation

South Broad Street

(Hudson Street & E. Ridgewood Avenue)

Road or Lane Closures

(7:00am 5:00 pm)

Monday- Friday

8 Parking Spots

As part of our electric reliability improvements in Bergen County, PSE&G will be performing utility underground work in the Village of Ridgewood. As of mid-January 2017, PSE&G will be performing the following activities in your area:

Excluding inclement weather delays, PSE&G anticipates working Monday –Friday, (7:00am 5:00pm)

Safety is our primary concern. PSE&G will work with the Ridgewood Police Department to minimize any traffic concerns or inconveniences to the public. Please be advised that Ridgewood Police Department may close additional spaces to ensure public safety. In addition, during construction, please refrain from going near our construction work zones.

The upgrades will enhance your electric capacity, system redundancy, and service reliability within the Village of Ridgewood, as well as surrounding communities. If you have questions or concerns, please call our toll free number at 1-877-678-5784

 