Traffic Alert - E. Ridgewood Avenue Paving Schedule

Traffic Alert:

PSE&G has hired a contractor to restore the pavement on  E. Ridgewood Avenue.  They will begin milling  E. Ridgewood Avenue, starting at Maple Avenue , and move east  on Friday, August 24th  for 4 days to be followed by paving.   This work will be completed by Labor Day, weather permitting.  To avoid possible traffic congestion in Paramus, this work schedule was amended to these new dates on 8/17/18. 

  • Hits: 3883